Kennecott’s smelter and refinery to undertake largest rebuild in nine years
Rio Tinto reports mined copper production of 138 thousand tonnes was 10% higher than the third quarter of 2021 due to higher grades and recoveries at Kennecott, partly offset by lower grades and recoveries at Oyu Tolgoi as a result of planned mine sequencing. Refined copper production guidance has been reduced to 190 to 220 thousand tonnes (previously 230 to 290 thousand tonnes), given further downside risk associated with Kennecott’s smelter and refinery performance, until we undertake the largest rebuild in nine years which is planned for the second quarter of 2023.
On 27 September, Rio Tinto approved $55 million in development capital to start underground mining and expand production at Kennecott. This will initially focus on the Lower Commercial Skarn area, which will deliver a total of around 30 thousand tonnes of additional copper through the period to 2027 alongside open cut operations. The first ore is expected to be produced in early 2023, with full production in the second half of the year. Underground battery electric vehicles are currently being trialled at Kennecott to improve employee health and safety, increase productivity and reduce carbon emissions from future underground mining fleets.
Bauxite production of 13.7 million tonnes was 2% lower than the third quarter of 2021 due to equipment reliability issues at Gove. Aluminium production of 0.8 million tonnes was 2% lower than the third quarter of 2021, and 4% higher than the prior quarter as the Kitimat smelter continues to ramp up and Boyne smelter cell recovery efforts progress as expected.
The Kitimat pot restarts are progressing but structural issues with the alumina conveyor system caused disruptions through the quarter slowing the rate of pot restarts. We continue to focus on full recovery during the course of 2023.
Titanium dioxide slag production of 310 thousand tonnes was 48% higher than the third quarter of 2021, due to community disruptions at Richards Bay Minerals in South Africa in 2021, and continued improved performance of operations at Rio Tinto Fer et Titane (RTFT), Canada.