Miracle possible!? – ESKOM: 100 days without load-shedding on 4 July

The improvement in the Energy Availability Factor is reflected in the country reaching the milestone of 100 days without load-shedding on 4 July. It is evident that Eskom’s performance showed a notable improvement starting in March 2024. Although 2024 began with a low EAF of around 50%, it increased steadily to approximately 65% by mid-year.

Eskom demonstrated consistent performance with its EAF remaining above 60% for the second consecutive month in June. There were no power outages reported in either May or

June. By early July, Eskom marked 100 straight days without power outages, reflecting significant progress in stabilising power supply. Planned maintenance increased by approximately 1,100 MW in June, while unplanned outages decreased compared to May, indicating more effective maintenance planning and operational efficiency. Electricity production has improved year-on-year, though May’s production was lower than in April and remains about 8.5% below pre-pandemic levels.

Leave a Reply

Your email address will not be published. Required fields are marked *